Project technical description

DESCRIPTION OF TECHNICAL SOLUTIONS

Foundation

Designed monolithic reinforced concrete piles foundation.
Underground parking structure

 
External walls - monolithic reinforced concrete with total thickness of 300 mm. The walls are insulated from the exterior with thermal insulation layer of 100 mm thickness polystyrene foam.
Columns and staircase walls are monolithic reinforced concrete.
External walls
 
Non-load bearing external walls - 200 mm „Aeroc Ecolight" blocks with 200 mm thickness insulation layer of Neopor. Facade finish layer - decorative plaster. The inner surface of external non-load bearing walls is plastered.
Design heat transfer coefficient of the outer wall μ= 0,125 W/m²K, respectively resistance R = 7,97 m²K/W.
Load bearing external walls are one-layer prefabricated reinforced concrete with 200 mm thickness insulation layer of Neopor. Facade finish layer - decorative plaster. Inner surface of external load bearing walls is concrete without plastering and any decoration.
Design heat transfer coefficient of the outer wall μ= 0.16 W/m²K, respectively resistance R = 6.24 m²K/W.

Internal walls and partitions
Walls between the apartments:
„Aeroc Acoustic" blocks, 300 mm thickness: 100 mm "Aeroc" blocks + 50 mm thickness mineral wool for sound insulation + 150 mm "Aeroc" blocks;
One-layer prefabricated reinforced concrete, 200 mm thickness.
This design meets the requirements for acoustic comfort class B.
Partitions of sanitary units - 100 mm thickness made of „Aeroc Acoustic" blocks. Sanitary units' internal wall surfaces are without plastering, puttying or painting.
Partitions - 100 mm gypsum board without puttying or painting.

Floor slab and ceiling
 
Floor slabs - reinforced concrete. Ceilings are without plastering and any finishing. 
Roof

 
The roof is not exploited. Roofing - welding bitumen cover.
Design thermal conductivity coefficient of the roof - 0.106 W/m²K, respectively resistance R= 9.42 m² K/W.
Windows and windowsills
 
Windows - wooden with triple-pane glass. Windows heat transfer coefficient - up to 1.0 W/m²K.
External window sills - tin coated with polyester, internal window sills - not installed.
Doors

Entrance to the apartment - single layer doors with two locks (one of them - "Master Key" system). Doors with a peephole. Internal apartment's doors are not installed.

Floors  The entire apartment is equipped with concrete levelling layer over soundproof panels.
Floors covering on concrete layer is not installed.

Balconies / terraces
 
Balcony floors - reinforced concrete slab. Upper slab finishing - natural concrete without additional waterproofing and coatings, lower slab finish - painted. Mounted tempered glass railings. Terraces' cover - paving.

Heating

 
Manifold type central district heating system. Mounted white bottom connection steel radiators with integrated thermostats. Underfloor heating is not installed. Heating in bathroom is connected with pipes from the district heating system to the heating device (towel rail is mounted by the residents), which will run by the apartment heating system during the heating season and during the summer - by using the electrical heater. Heat accounting system is installed.
Staircases have radiators of lower connection with integrated thermostatic valves and thermostatic heads.
Underground parking and its technical premises - without heating.

Ventilation
The common recuperating ventilation system is equipped. Using this mechanical system for ventilation air circulates without being sensed by the persons present in the premises and is evenly distributed throughout the room. Warm air outgoing from the room heats the incoming cold air in the recuperator, therefore supplied fresh air is at room temperature. Such ventilation does not cool off the rooms and helps to save about 30% of the heat. In addition, each kitchen is equipped with air exhausting ducts from kitchen hoods.
Horizontal ducts in the premises are uncovered.

Air conditioning
The dwelling has indoor cooling system. The project provides required power for cooling devices and their installation points on the roof and in the premises. The builder installs pipelines between the outer and inner blocks of the wall and equipment is installed on buyer's demand.
 
Water supply
Connected to the district main networks. The dwelling is equipped with hot and cold water stands. Pipes are laid to the sanitary and kitchen appliances provided in the project and completed with nozzles and blind flanges. Cold and hot water counters will be installed in the apartment. Plumbing appliances are not installed.
 
Wastewater Household waste water stands are installed. Pipes with blind flanges is laid to the sanitary units and kitchen appliances as provided in the project.
 
Power supply The electrical accounting of common premises and apartments is equipped. Inside the apartment there is installed electrical panel with automatic breakers and connected electrical voltage (power is connected after signing the contract with LESTO). There are fire retardant electrical wires with double insulated copper conductors and hidden distribution boxes in the apartments. Sockets, switches and lights are not installed.
Electric plugs are installed in balconies.
 
Weak currents Each floor is equipped with the communication box for low voltage networks (television, telephone) in the staircase. PVC installation pipes are laid from these boxes to the low voltage wiring distribution boxes in the apartments. Pipes for telephone and cable television cables are also laid to the apartment's distribution box. Apartments are provided with communication wires are with copper conductors and hidden distribution boxes. Sockets for telephone, television and internet networks are not installed. Fire sensors are fitted in accordance to the project requirements. A video phone system is equipped for residents to monitor guests' access of the entrance doors in the courtyard and staircase. Residents can access to the apartment by unblocking the electromagnetic lock using a button or individual password (formulated by themselves).
 
Video surveillance system
 
Video surveillance system is equipped. Video surveillance cameras are not installed.
Lightning protection Lightning protection system has active lightning conductor connected to the grounding system.


COMMON PREMISES

Stairwells, halls

 
Staircases - precast reinforced concrete stairs. Staircase entrance doors - aluminium frame with glass pane and the built-in video intercom. Walls finishing - puttying and painting. Suspended ceilings. Mounted lightings controlled by motion and heating devices. Stairs and landings are covered with stone tiles. Metal railings.
 
Elevators

 
The dwelling house is equipped with an elevator. It allows to access all floors - from underground car parking in the basement up to the top sixth floor.
 
Landscaping


The following is installed: children playground, benches. Pavements, sidewalks, landscaping, street and yard lighting and other landscaping elements are installed according to the site plan project. Inner courtyard is closed and designed only for residents and their guests.
Underground
parking and
bicycle storages



Internal walls and partitions - monolithic or masonry blocks (not plastered, unpainted), bicycle storage's part above the doors - metal net. Each bicycle storage has surface-mounted electrical wiring, lighting, plug switch and painted metal lockable doors.
The access to the underground parking through the automatic lifted gate with an automatic gear.
Waste collection scheme The premise is in underground floor of the building next to the driveway of the underground car parking. It has entries from the street and underground parking. Premise is equipped with ventilation system.